§ 57.705. Contents of SIP Compliance Schedule required by § 57.201(d) (2) and (3).
163 words·~1 min read·
/us/cfr/t40/s§ 57.705·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
This section applies to smelters which are required to submit a SIP Compliance Schedule as discussed below.
(a)Each SIP Compliance Schedule required by § 57.201(d)
(2)and
(3)must contain the following elements:
(1)Description of the overall design of the SO2 control system(s) to be installed;
(2)Descriptions of specific process hardware to be used in achieving compliance with the SIP emission limitation including gas capacity values;
(3)The date by which contracts will be let or purchase orders issued to accomplish any necessary performance improvements;
(4)The date for initiating on-site construction or installation of necessary equipment;
(5)The date by which on-site construction or installation of equipment is to be completed;
(6)The date for achievement of final compliance with SIP emission limitations; and
(7)Any other measures necessary to assure compliance with all SIP requirements as expeditiously as practicable.
(b)Operations of SCS. Smelters to which § 57.705 is applicable must comply with all elements of § 57.703.